Trieu bridge closure scheduled for Nov

THURSDAY, 24/09/2020 08:43:24

It is expected that the two bridge ends will be joined on November 20 and the bridge will be put into use on December 30, 2020.

According to Pham Thanh Tuan, Head of the Management Board of Investment and Construction Projects of Dong Trieu provincial town, Quang Ninh province, the construction volume of Trieu bridge building project has reached about 80%.

The construction unit finished building piers, supports, and bridge substructure and is conducting cantilever casting, installing guardrails, and constructing the bridge floor.

It is expected that the two bridge ends will be joined on November 20 and the bridge will be put into use on December 30, 2020.

At present, the approach to Trieu bridge in Dong Trieu provincial town, more than 2 km long, is being paved with an aggregate base course, and the road surface is going to be covered. The road construction will be completed before October 30.

Quang Ninh provincial government is the investor of the project to build Trieu bridge and the approach in Dong Trieu provincial town with a total investment of VND430 billion.

The bridge is more than 700 m long, crosses the Kinh Thay river, starts in Hong Phong commune, Dong Trieu provincial town, and ends in That Hung ward, Kinh Mon provincial town, Hai Duong province.

To create traffic synchronization when Trieu bridge is put into use, Hai Duong authorities are speeding up the construction of a path from the bridge to provincial road 389.